From the time we close on a lot, construction of a home takes approximately 7 months. If you purchase one of our spec homes you will be able to customize the house for your needs and save time and money. Spec homes are usually ready in 4-5 months once they are listed for sale.
- Month 1
- Development of site plan, finalize construction drawings, final pricing, owner material selection begins, permitting
- Month 2
- Demolition of existing building and clearing of site, regarding and digging of basement, footings, basement walls, under slab plumbing, and basement slab.
- Month 3
- Framing, windows and exterior doors installed, roof, cornice work.
- Month 4
- Rough-in plumbing, HVAC, and electrical. Inspections and sheet rock. Brick work and exterior painting.
- Month 5
- Trim work, interior painting, interior doors, tile work, kitchen cabinets, hardwood flooring
- Month 6
- Final electrical, HVAC, Plumbing, counter tops, install lighting, finish hardwoods, install carpet.
- Month 7
- Punch out, final inspections, final closing, and move-in.
|